OPS935 Project Management
2020 Apr 1 OPS936 Trimester 1, 2020 Page 1 of 3
UOW Sydney Business School
Faculty of Business
OPS935
Project Management
Assessment 3
Trimester 1, 2020
| Directions to students | ALL questions to be answered. There are two (2) sections to be answered. This examination is worth 50% of your final mark. You must achieve at least 50% in this examination and gain at least 50% overall in the subject to pass. You must write your answer with your own words and submit a separate sheet with your number and full name on the top of the first page via Moodle / Turnitin. |
| Due Date | 20 Abril 2020 (Monday) Final submission time: 5pm |
2020 Apr 1 OPS936 Trimester 1, 2020 Page 2 of 3
SECTION A: Short Answer Questions (worth 50 marks)
| 1. Discuss the relationship between the IPO and ITO models with project success dimensions. Give original examples – maximum of three paragraphs. |
(10 marks) |
| 2. Discuss the four phases of a typical project life cycle – maximum of five paragraphs. |
(10 marks) |
| 3. In one paragraph, explain why is the Utilisation Matrix important? Give an original example – maximum of one paragraph. |
(10 marks) |
| 4. In three paragraphs, discuss the behaviour of level of effort, cost of changes and degree of uncertainty per phase across project life cycle – maximum of four paragraphs. |
(10 marks) |
| 5. Explain the project management approach that you selected to develop the project management plan with your group for assessment 2 (Stage-Gate, CCPM, MSF, RUP, PRINCE2, Agile or Six Sigma) – maximum of maximum: five paragraphs. |
(10 marks) |
SECTION B: Practical (worth 50 marks)
Given the Gantt chart provided in the next page,
| 1. Identify the tasks that belong to the critical path. (10 marks). | (10 marks) |
| 2. Identify five problems in this Gantt chart and propose solutions to correct each one. Use the project management tool provided in class. |
(10 marks) |
| 3. Add and justify five new tasks aimed at avoiding cost of non-conformance. | (10 marks) |
| 4. Identify five risks in this Gantt Chart and define mitigation and contingency plans for each one. |
(20 marks) |
2020 Apr 1 OPS935 Trimester 1, 2020 Page 3 of 3
Gantt Chart
Note: The numbers below the months are the days that each week starts (Mondays)
End of Assessment